The dirt road located in Bradu town, Avrig city, Sibiu county, was modernized through the execution of the following categories of works:
-
execution of two layers of asphalt covering on a foundation of crushed stone and ballast
-
ensuring the drainage of rainwater through the execution of perimeter ditches on the roadway
-
execution of tubular floors, at the accesses to properties and side roads, from PPMI SN10 Ø400 & 500 mm, with a minimum length of 6.0 m, with reinforced concrete slabs and drums, cast monolithically
-
ensuring the safety of road traffic
The modernization of the street increased the level of comfort of the residents in the area and improved road safety.
Duration of execution: 5 months
Period of execution: 2021